Background:
Because there are many components in motion, we've compiled a list outlining requirements, clarifications, and areas of responsibility to ensure the seamless integration between Inlet and the lock system.
Read more about the security principals for Inlet and the connections to locks here.
Practical and Technical Requirements:
- Danalock is installed and fully commissioned in the usual manner by the installer.
- The lock needs to be connected to a danabridge.
- Once all the locks are active and set up, Inlet needs to be notified by mail to support@inlet.tech:
- Customer Name
- Information on what locks should set up.
- Inlet sends an approval link that the customer in return must click on.
- The customer clicks on the link and verifies themselves with danalock.
- Notify Inlet on support@inlet.tech again when everything is ready, and the process can proceed.
- Inlet retrieves IDs from the locks to configure Inlet with the locking system.
- Inlet provides information to the main system/booking system for testing.
- Inlet requires a minimum of 2 weeks of testing with the main system/booking system after the installer has completed all the steps above.